Udon Thani City Gate construction delayed past Expo

Udon Thani City Gate construction delayed past Expo

Thairath•Society•50m ago

Reader Briefing

The Udon Thani Provincial Public Works and Town & Country Planning office addresses public criticism regarding the incomplete Udon Thani City Gate.

  • •The Udon Thani City Gate construction was not completed in time for the World Horticultural Expo.
  • •Siam Butyojantho attributed the delay to the contractor's liquidity problems.
  • •The project's structure is finished, but decorative details and signage remain incomplete.
  • •Approximately 5% of the work remains, valued at roughly 2 million baht.

Overview

  • •The Udon Thani City Gate construction structure is complete, but decoration, landscaping, and signage are still pending.
  • •Siam Butyojantho stated that the primary cause of the delay is the liquidity of the contractor and workers.
  • •Siam Butyojantho denied allegations of budget embezzlement and claimed he and the inspection committee spent their own money to keep work moving.
  • •Local residents and social media users criticized the gate for being unattractive and suspected corruption.
  • •Ongkan Kaewkham reported that 5% of the work remains, including electrical systems for 10 rooms and patterned concrete flooring.
  • •There is currently 10.559 million baht of the project budget that has not yet been withdrawn.
  • •Ongkan Kaewkham stated the contractor will complete the project despite potential fines or incomplete payment.
  • •On November 4, 2026, reports emerged regarding the social media drama following the opening of the World Horticultural Expo Udon Thani.

Full article content is available on the original source.

Read on Thairath (Thai Version)Read on Thairath (English Version)

Source: Thairath (Original)

Key Quotes

Siam Butyojantho
"I remember my own words that I would have it finished before the Horticultural Expo."
ผมจำคำพูดตัวเองได้ว่าจะให้เสร็จก่อนพืชสวนโลก
Ongkan Kaewkham
"The goal is that the work was accepted, promised to the people and government agencies that it must be finished."
เป้าหมายคือ งานรับมาแล้ว รับปากพี่น้อง รับปากส่วนราชการไว้ว่าต้องเสร็จ

Key Entities

Person

Siam Butyojantho(สยาม บุตรโยจันโท)
The Public Works and Town & Country Planning officer of Udon Thani.
Ongkan Kaewkham(โองการ แก้วคำ)
The project control engineer from the contracting company.
Somchai Promtho(สมชาย พรมโท)
A noodle shop owner located approximately 200 meters from the city gate.
Mongkol Nonkhamwong(มงคล นนท์คำวงค์)
A shoe repair shop owner located under the pedestrian bridge near the city gate.

Organization

Department of Public Works and Town & Country Planning(กรมโยธาธิการ)ℹ️
The government department represented by Siam Butyojantho.
Udon Thani Provincial Administrative Organization(อบจ.อุดรธานี)
The organization that provided the decorative flags for the city gate.
24th Military District(มทบ.24)
The military district located near the Udon Thani City Gate.

Place

Udon Thani City Gate(ซุ้มประตูเมืองอุดรธานี)
A construction project located in front of the 24th Military District on Thahan Road, Udon Thani Municipality.