Udon Thani City Gate Construction Delayed Despite Expo

Matichon•Society•19d ago

Reader Briefing

Udon Thani Public Works and Department of Public Works and Town & Country Planning admit the city gate construction was not completed in time for the World Horticultural Expo.

  • •The Udon Thani City Gate construction is incomplete despite the start of the World Horticultural Expo and a cabinet meeting.
  • •Social media and local media criticized the project's aesthetics and alleged budget corruption.
  • •Siam Butyojanto attributed the delay to the contractor's liquidity issues.
  • •Approximately 5% of the work remains, with around 10.559 million baht in budget not yet disbursed.

Overview

  • •The Udon Thani City Gate structure is complete, but decoration, detailing, and landscaping are unfinished.
  • •Siam Butyojanto, the Udon Thani Public Works and Town & Country Planning Officer, acknowledged that the project did not meet the deadline he set for the World Horticultural Expo.
  • •Siam Butyojanto stated that the primary cause of the delay is the liquidity of the contractor and workers.
  • •Ongkan, the project control engineer, reported that 5% of the work remains, valued at approximately 2 million baht.
  • •The contractor continues work on external layouts, interior electrical systems for 10 rooms, and concrete flooring to complete the project.
  • •Siam Butyojanto denied allegations of budget corruption, claiming he and the inspection committee personally contributed over 200,000-300,000 baht to ensure certain tasks were completed.
  • •Local residents Somchai and Mongkol observed that construction has been ongoing for about two years and involved multiple contractors.

Full article content is available on the original source.

Read on Matichon (Thai Version)View in Google Translate

Source: Matichon (Original)

Key Quotes

Siam Butyojanto
"I remember my own words that it would be finished before the Horticultural Expo."
จำคำพูดตัวเองได้ว่าจะให้เสร็จก่อนพืชสวนโลก
Siam Butyojanto
"The only problem is liquidity."
ปัญหาเดียวคือสภาพคล่อง
Ongkan
"Work now remains at about 5%, valued at approximately 2 million baht."
งานตอนนี้เหลืออยู่ประมาณ 5% ตีเป็นมูลค่าประมาณ 2 ล้านบาท

Key Entities

Person

Siam Butyojanto(สยาม บุตรโยจันโท)
The Udon Thani Public Works and Town & Country Planning Officer.
Ongkan(โองการ)
The project control engineer from the contractor company.
Somchai(สมชาย)ℹ️
A noodle shop owner located approximately 200 meters from the city gate.
Mongkol(มงคล)
A shoe repair shop owner who has worked under the pedestrian bridge for over 20 years.

Organization

Udon Thani Public Works and Town & Country Planning(โยธาธิการและผังเมืองอุดรธานี)
The government agency responsible for the Udon Thani City Gate project.
Udon Thani Provincial Administrative Organization(อบจ.อุดรธานี)
The organization that provided the decorative flags (Thung) for the city gate.
24th Military District(มทบ.24)
The entity located in front of which the Udon Thani City Gate is being built.
Udon Thani City Municipality(เทศบาลนครอุดรธานี)
The local government area where the city gate is located.

Place

Udon Thani City Gate(ซุ้มประตูเมืองอุดรธานี)
The construction project located in front of the 24th Military District on Thahan Road.