CP Requests High-Speed Rail Contract Termination; SRT Prepares Airport Link Plan
Matichon•Economy•
Full article content is available on the original source.
Source: Matichon (Original)
Key Quotes
"If the private sector still insists on not being able to proceed with the project and wishes to exercise their legal rights, then the option of contract termination will be considered."
หากเอกชนยังยืนยันว่าไม่สามารถดำเนินโครงการต่อได้และประสงค์ใช้สิทธิตามกฎหมาย จึงจะเข้าสู่การพิจารณาแนวทางที่จะสิ้นสุดสัญญา
"Regarding the impact on Airport Rail Link services if the contract is terminated,"
ขณะที่ดีพอต่อการให้บริการ Airport Rail Link หากมีการสิ้นสุดสัญญา
Key Entities
Organization
The private sector company that is a contractor for the three-airport high-speed rail project.
The state-owned railway company involved in the high-speed rail and Airport Rail Link projects.
SRT Board(คณะกรรมการ(บอร์ด) รฟท.)
The governing board of the State Railway of Thailand which discusses and makes decisions on railway projects.
Eastern Economic Corridor Policy Committee (EEC)(คณะกรรมการนโยบายเขตพัฒนาพิเศษภาคตะวันออก (สกพอ.))
The committee responsible for policy in the Eastern Economic Corridor, involved in the high-speed rail project.
EECO
Abbreviation for the Eastern Economic Corridor Policy Committee, involved in the high-speed rail project.
Asia Erasun Company Limited(บริษัท เอเชีย เอราวัน จำกัด)
The private company, a subsidiary of CP, that is the contractor for the three-airport high-speed rail project.
The Thai Cabinet of ministers, whose approval is required for key decisions regarding the high-speed rail project.
The legal body that has reviewed the draft contract amendments for the high-speed rail project.
Person
Anan Phothinamdaeng(นายอนันต์ โพธิ์นิ่มแดง)
The Governor of the State Railway of Thailand (SRT) providing updates on the high-speed rail project.
Law
Memorandum of Understanding (MOU)(บันทึกข้อตกลง (MOU))
The agreement governing the current operations of the Airport Rail Link, which is nearing its expiration.